Bid Scout · Tue Nov 10, 2026 · 7:08 AM ET

We covered why mandatory site meetings matter, and what the plan-taker list tells you, in Mandatory Site Meetings and Plan-Taker Lists. This post is the practical part: what to do before, during and after the walk so the trip actually improves your electrical price.

Before you leave

What to bring

What to record on site

  1. Your sign-in. Note the time, who signed for your firm, and the buyer's representative.
  2. Existing electrical gear. Photograph nameplates on the service, switchgear, panels and transformers you'll touch, and note anything that doesn't match the drawings.
  3. Access and working limits. Ceiling space, room to get equipment in, occupied areas, security escorts, and anything that hints at after-hours or shutdown work.
  4. Distances and routing. Measure the runs you're unsure of. Note where conduit can and can't go.
  5. Questions as they come up. Write them down. Don't count on a verbal answer.
  6. Who else showed up. The other firms in the room are your competition, or the GCs you may sub to.

Why verbal answers don't count

York's RFT-3850-26 notice says no questions will be asked or answered during its site meeting, and all questions go through the portal's "Submit a Question" feature. Thunder Bay's Information to Tenderers template says verbal answers are only binding when confirmed by written addenda. The LCBO notice says verbal responses at site visits are neither official nor binding. Thunder Bay's template also says tenderers can't claim after submitting that they misunderstood site conditions.

So whatever you heard on the walk, put it in writing.

Within 24 hours of the walk

If the buyer's documents and this checklist ever disagree, the documents win.