Bid Scout

How to read a tender

RFQ, RFT or RFP: How the Solicitation Type Changes the Way Your Electrical Bid Is Judged

Bid Scout · Wed Nov 18, 2026 · 7:08 AM ET

The three letters in front of a bid number tell you how the buyer will pick a winner. Read them before you price, because an RFT, an RFQ and an RFP reward different things. Here's how Ontario buyers define each one, with open electrical bids we checked on Wed Nov 18.

RFT: lowest compliant price wins

A Request for Tender is used when the work can be fully specified. The City of Hamilton's procurement policy defines an RFT as a formal request for prices "where the Goods and/or Services are able to be fully defined or specified at the time of the request" (Hamilton By-law 22-255). The Town of Whitby is more direct: the "lowest priced compliant tender, from a compliant bidder, is accepted without negotiation" (Whitby Procurement Policy F-080).

That puts all the weight on two things: your number, and compliance. A missed form or signature can sink the lowest price. Example: York Region's RFT-3850-26, electrical substation maintenance at various Region facilities, closes Fri Dec 11 at 1:00 PM and takes electronic bids only. If you're bidding an RFT, the bid bond and forms matter as much as the take-off (see our bonds and insurance post).

RFQ: price on smaller or simpler work

A Request for Quotation is usually the lighter-weight version. Hamilton calls it "an informal request for prices" on purchases between $10,000 and $100,000 "where comprehensive technical Specifications can be developed." The City of Toronto says an RFQ "focuses on gathering information on price and quality level per item, payment terms, contract length" (City of Toronto: Understanding the Procurement Process). Toronto's procurement by-law adds that for RFTs and RFQs, best value may be "the lowest cost bid meeting technical specifications and supplier qualifications" (Toronto By-law 960-2016).

Thresholds differ from one buyer to the next, so an RFQ is not always a small job. The City of Barrie has one open on bids&tenders right now. FIN2026-217Q, installation of two outdoor diesel generator sets at Barrie Fire & Emergency Services Headquarters, closes Tue Dec 8 at 2:00 PM. The listing says it's subject to the Municipal Buy Ontario Directive.

Read the RFQ's own evaluation section. Don't assume it's price-only.

RFP: price is one score among several

A Request for Proposal is used when the buyer wants your approach, not just your number. Hamilton's definition covers work that "may not be able to be fully defined or specified," or where "alternate methods are being sought." Whitby says price is a mandatory evaluation factor "but usually not the primary evaluation factor," and an RFP may allow negotiation before award.

For hospitals, school boards, colleges and universities, Ontario's Broader Public Sector Procurement Directive says the documents must "clearly outline mandatory, rated, and other criteria," with the weight of each one. Criteria can only change by addendum.

Electrical work shows up as RFPs more often than you'd think. On Wed Nov 18:

On an RFP, the lowest price can lose. Find the scoring grid in the documents and write to it: crew experience, references, schedule and method usually carry the rated points.

Two more you'll see: RFPQ and RFSQ

These come before the bid. Hamilton defines a Request for Prequalification as a process to decide whether a vendor can do the work, run "before a RFP or RFT is issued," after which "only prequalified vendors are eligible to submit a Bid." York's RFTC-3919-26-25026 (security system and motorized gate replacement, closes Fri Nov 20 at 1:00 PM) is open only to contractors prequalified under an earlier RFSQ. Niagara Region's 2026-RFSQ-167, a construction contractor roster that includes electrical, closes Fri Nov 27 at 2:00:59 PM. More on getting on these lists in our prequalification post.

A quick check before you price

  1. Read the letters, then the evaluation section. The section wins if they disagree.
  2. RFT or RFQ: tighten the number and run a compliance checklist.
  3. RFP: budget time to write. Points for method and experience can outweigh a few percent on price.
  4. RFPQ or RFSQ: missing it can lock you out of the tenders that follow.

Get a free sample brief

Email jay@bidscoutontario.com with your trade and region.

Email jay@

Sources